A Notice of Refusal means L&I can't issue your zoning permit because the plan breaks one or more zoning rules for that address. Each problem is listed on the notice with the rule it breaks. You can change the plan, or appeal to the Zoning Board of Adjustment within 30 days of the refusal date. An appeal usually takes months, so start right away.
Have your notice? Get it explained →
Rules last checked November 24, 2026. More business guides (licenses, reopening) are coming soon.
Common problems on a refusal
0 of 6 checkedThe most common refusal (Table 14-602-1). For example, an office, studio, shop or storage in a residential district. Fix: choose a use the district allows, or appeal for a variance.
Some residential districts allow only one principal use per lot (Section 14-401). A building with apartments plus a shop can be refused for this alone.
The notice lists the limit and your planned height side by side. Fix: lower the design, or appeal.
Each district limits how much of the lot can be built on (often 80% on corner lots). Fix: shrink the footprint, or appeal.
Minimum yard depths apply. The notice shows the required and proposed depth.
In some districts a garage must be reached from a shared driveway, alley or rear street, not the front street (Section 14-803).
What to do next
0 of 8 checkedYou have 30 days from the refusal date to appeal. Missing it means starting over with a new application.
If a small change fixes every problem, revise the plan instead. Otherwise appeal to the Zoning Board of Adjustment (ZBA) for a variance or special exception.
Individuals may represent themselves. Companies, including LLCs and nonprofits, must be represented by a Pennsylvania attorney.
Send the appeal application, Project Information Form, the signed Notice of Refusal and the fee. Since August 1, 2026: $125 for an existing one- or two-family home or an affordable housing project, $811 for all other properties. If you got the refusal in eCLIPSE you can file online.
Within 20 days of the ZBA's email, contact the coordinating Registered Community Organization to set a meeting, and send the required notice to neighbors.
The RCO should try to hold it within 45 days of filing and sends a summary to the ZBA.
Hang an 11x17 poster on each street frontage, plus a copy of the refusal, at least 21 days before the hearing. Take time-stamped photos.
Submit exhibits at least 14 days before the hearing. As of March 2026, a regular hearing takes about 180 days to schedule; an accelerated hearing costs $995 and takes about 140 days.